Preparatory works have commenced for the expansion of the passenger terminal at Riga Airport, with the construction site currently being established, including temporary facilities, access roads and the contractor’s administrative area. During the first phase of construction, running from December this year until September next year, the contractor will build new access roads and adapt existing roads, public transport lanes and parking facilities.
The second phase of the project will begin in mid-next year, when the existing elevated access ramps to the departures hall entrances on the second floor will be demolished. As a result, access arrangements to the terminal will change significantly. All passenger and vehicle traffic serving the existing terminal building will be redirected to ground level (Level 1). To ensure convenient access for all passenger groups, including passengers with reduced mobility, temporary entrances and exits will be created, while the newly constructed roads and parking facilities will be brought into operation.
Construction of the new terminal building, representing the third phase of the project, is scheduled to begin in autumn next year and be completed by summer 2030. The new facility will occupy part of the area currently used by the short-term car park. P1. It will include a new passenger check-in hall, waiting areas, a security screening zone and an arrivals baggage reclaim hall. The project will also redevelop the surrounding outdoor areas, including access roads, parking facilities and public spaces.
The introduction of new passenger processing and security technologies will significantly enhance the passenger experience, improve comfort and operational efficiency, and provide the infrastructure required to support Riga Airport’s future growth.
Throughout the construction period, Riga Airport will remain fully operational. However, passengers and visitors should expect temporary changes to traffic flows and access routes when travelling to and from the airport. Particular attention will be paid to ensuring accessibility for people with mobility impairments and other functional limitations. The contractor, in cooperation with the airport, will provide timely information about all upcoming changes.
The terminal expansion project will deliver approximately 20,000 square metres of new terminal space, while a further 29,500 square metres will be developed as roads, pavements, landscaped public areas and green spaces.
The terminal expansion will be delivered by the RIXLA consortium, established by LNK Industries and Arčers. The contract has been awarded under the terms of the FIDIC Yellow Book. Engineering, BIM management, certified BREEAM assessment services, design review and construction supervision are being provided by a joint venture of Latvia’s P.M.G. and Lithuania’s Incorpus. The project is targeting a BREEAM Very Good sustainability certification rating.
The total investment in the terminal expansion is estimated at EUR 98 million. Financing has been secured through equal participation by the European Bank for Reconstruction and Development (EBRD), the Nordic Investment Bank (NIB) and OP Corporate Bank plc Latvia Branch.
In addition, funding will be available for equipping the terminal with the latest generation of passenger handling and aviation security technologies that comply with EU standards. The new systems will help ensure the highest levels of aviation security, accessibility and passenger service quality while supporting the airport’s long-term development objectives.